COD, Long and Easy to Bend: Facilitates Installation and
Saves Time for the Installation Fiber Optic Cable.
COD, if used as a cable duct, should be laid in accordance
with all items prescribed in the Electrical Equipment Technique
standard and all other applicable laws and regulations. At the
construction site, therefore, COD should be laid in accordance
with the standardized laying procedures described below.
Trenching
The number of laid COD determines the trenching width. However,
the width should be determined with due consideration of economy
and safety associated with the laying operation; it is required
to carry out maximum of safety procedures so that no landslide
is caused at the minimum of width. The lowermost COD should
not be laid directly on rocks and sharp pebbles. It is recommended
that the excavated area should be leveled and then covered with
sand or soft soil before laying COD.
COD should be laid carefully so as to prevent soil, sand and
water from entering COD through the end mouth. If coiled COD
delivered to the site, it should be laid in accordance with
the following procedure. The coiled COD should be uncoiled along
the trenched ground, being held by laborers so that it is well
laid inside of the trench. Make it sure to uncoiling is stretched
straight.
Perfect alignment
When 2 or more COD are to be laid in parallel, the respective
COD should be arranged with the specified distance as shown
in Fig. A. To this end, a simple gauge shown in Fig. B should
be prepared to straighten the laid COD every 3 or 4 meters.
The straightened COD should be held in place with sand or
the equivalent, and then the gauge should be removed. COD
should not be laid on pipe saddles, which have been used for
conventional Hume pipe.
|
|
| |
|
|
|
|
|
|
Trench Dimension:
For economical operation, particularly where paving is
involved, the trench dimension should be no greater than the specified
dimension. Generally, 0.3 m(W) x 0.6 (H) dimension is recommended
up to laying of 2 lines of COD regardless of numbers of inner ducts.
|
|
|
|
Trench Bedding:
If not specified in specifications, mechanical leveling of the trench
bed by excavator will be sufficient.
|
|
|
|
Laying COD:
After the trench is being excavated, either release-and-place the
COD on the ground surface along with the trench to put it into such
trench or lay directly into the trench by releasing the COD from the
spool. To carry out backfill according to the job specifications after
required connection being properly made on the ground surface.
|
|
|
| |
|
|
 |